Buyer Name: Kier Transportation - CP7 NWC
Buyer Address: 2nd Floor Optimum House, Clippers Quay, M503XP, UK
Contact Name: Mark Thompson
Contact Email: mark.thompson@kier.co.uk
Contact Telephone: 07880787625
Buyer Name: Kier Transportation - CP7 NWC
Buyer Address: 2nd Floor Optimum House, Clippers Quay, M503XP, UK
Contact Name: Mark Thompson
Contact Email: mark.thompson@kier.co.uk
Contact Telephone: 07880787625
"The planned introduction of longer train services to the Airport in response to future demand growth will mean that double stacking arrangements of trains as currently used will no longer be viable. Through the project's Delivery Steering Group, Northern and TransPennine Express have carried out analysis which has identified that additional platform capacity is needed at the airport in order to realise the full benefit of longer train services serving the airport. The scheme is part of a package of proposed measures in the Manchester area that are being designed/planned to boost capacity and resilience, emanating from the Cross Manchester Capacity and Reliability Improvement Study. Improving the operation of train services in the centre of Manchester and providing further capacity at Manchester Airport station, aligns with the strategic aims of Network Rail, TfGM, TfN and the wider industry. This project in in Tranche 1 of the Manchester and North West Transformation Programme (MNTP): A remodelling of the station at Manchester Airport, specifically a platform addition or extension of multiple platforms, or provision of a new turnback facility, will be essential to accommodate the planned implementation of longer rolling stock services. The redevelopment of these platforms will enable permissive working of two 6x24m (144m) trains, in two of the four platforms at the Airport Station. This will allow for the unaltered retention of all existing TOC services both originating and terminating at the Airport Station under 'double-stacking' conditions. The scope areas for this package are as follows: The piling mat location along S2 and S1 walls will need to be installed to accommodate the arrival of the SF95 CFA piling rigs. The excavation of material and installation of temporary works for the pile mats will be on 3rd party land belonging to the Clayton Hotel and MAG. - Clayton Hotel Wall Removal/Relocation and Reinstatement upon completion. - Remove Fencing - Piling Mat Installation (S1 134m, S2 194m) - Screw Piles - Stone up the area adjacent to the UU area (already deveged) - Install Railway access steps
No linked documents found for this notice.
External Link: https://www.contractsfinder.service.gov.uk/Notice/22a58595-1e7e-45f7-8219-c50361b9fec8
Link Description: Opportunity notice on Contracts Finder
External Link: https://www.competefor.com/business/viewOpportunityDetailsSupplier.html?id=107025294
Link Description: Please follow this link to view the notice.
Document Description: Opportunity notice on Contracts Finder
Document Description: Please follow this link to view the notice.
{
"buyer": {
"id": "GB-CFS-294297",
"name": "Kier Transportation - CP7 NWC"
},
"date": "2026-02-10T11:00:04Z",
"id": "22a58595-1e7e-45f7-8219-c50361b9fec8-882936",
"initiationType": "tender",
"language": "en",
"ocid": "ocds-b5fd17-884001d1-7f09-454f-9e07-e5113c336614",
"parties": [
{
"address": {
"countryName": "UK",
"locality": "Clippers Quay",
"postalCode": "M503XP",
"streetAddress": "2nd Floor Optimum House"
},
"contactPoint": {
"email": "mark.thompson@kier.co.uk",
"name": "Mark Thompson",
"telephone": "07880787625"
},
"id": "GB-CFS-294297",
"identifier": {
"legalName": "Kier Transportation - CP7 NWC"
},
"name": "Kier Transportation - CP7 NWC",
"roles": [
"buyer"
]
}
],
"tag": [
"tender"
],
"tender": {
"classification": {
"description": "Piling",
"id": "44212400",
"scheme": "CPV"
},
"contractPeriod": {
"endDate": "2026-07-13T23:59:59+01:00",
"startDate": "2026-05-04T00:00:00+01:00"
},
"datePublished": "2026-02-10T11:00:04Z",
"description": "\"The planned introduction of longer train services to the Airport in response to future demand growth will mean that double stacking arrangements of trains as currently used will no longer be viable. Through the project\u0027s Delivery Steering Group, Northern and TransPennine Express have carried out analysis which has identified that additional platform capacity is needed at the airport in order to realise the full benefit of longer train services serving the airport.\r\n \r\n The scheme is part of a package of proposed measures in the Manchester area that are being designed/planned to boost capacity and resilience, emanating from the Cross Manchester Capacity and Reliability Improvement Study. Improving the operation of train services in the centre of Manchester and providing further capacity at Manchester Airport station, aligns with the strategic aims of Network Rail, TfGM, TfN and the wider industry. This project in in Tranche 1 of the Manchester and North West Transformation Programme (MNTP):\r\n \r\n A remodelling of the station at Manchester Airport, specifically a platform addition or extension of multiple platforms, or provision of a new turnback facility, will be essential to accommodate the planned implementation of longer rolling stock services.\r\n \r\n The redevelopment of these platforms will enable permissive working of two 6x24m (144m) trains, in two of the four platforms at the Airport Station. This will allow for the unaltered retention of all existing TOC services both originating and terminating at the Airport Station under \u0027double-stacking\u0027 conditions.\r\n \r\n The scope areas for this package are as follows:\r\n \r\n The piling mat location along S2 and S1 walls will need to be installed to accommodate the arrival of the SF95 CFA piling rigs. The excavation of material and installation of temporary works for the pile mats will be on 3rd party land belonging to the Clayton Hotel and MAG.\r\n \r\n - Clayton Hotel Wall Removal/Relocation and Reinstatement upon completion.\r\n - Remove Fencing\r\n - Piling Mat Installation (S1 134m, S2 194m)\r\n - Screw Piles\r\n - Stone up the area adjacent to the UU area (already deveged)\r\n - Install Railway access steps",
"documents": [
{
"datePublished": "2026-02-10T11:00:04Z",
"description": "Opportunity notice on Contracts Finder",
"documentType": "tenderNotice",
"format": "text/html",
"id": "1",
"language": "en",
"url": "https://www.contractsfinder.service.gov.uk/Notice/22a58595-1e7e-45f7-8219-c50361b9fec8"
},
{
"description": "Please follow this link to view the notice.",
"documentType": "tenderNotice",
"id": "2",
"url": "https://www.competefor.com/business/viewOpportunityDetailsSupplier.html?id=107025294"
}
],
"id": "C4N107025284",
"items": [
{
"deliveryAddresses": [
{
"countryName": "United Kingdom",
"region": "North West"
},
{
"countryName": "British Oversea Territories"
},
{
"countryName": "Channel Islands"
},
{
"countryName": "Europe"
},
{
"countryName": "Isle of Man"
},
{
"countryName": "Rest of the World"
},
{
"countryName": "United Kingdom"
}
],
"id": "1"
}
],
"mainProcurementCategory": "works",
"minValue": {
"amount": 250000,
"currency": "GBP"
},
"procurementMethodDetails": "",
"status": "active",
"suitability": {
"sme": true,
"vcse": false
},
"tenderPeriod": {
"endDate": "2026-02-20T17:00:00Z"
},
"title": "Manchester International Airport - Temporary Works Piling Enabling Works",
"value": {
"amount": 500000,
"currency": "GBP"
}
}
}